Midstream Compressor Station — Northeast British Columbia
412 driven steel H-piles, dynamic compaction of 18,000 m² of granular pad, and installation of settlement monitoring array.
Pile production completed 11 days ahead of an aggressive 68-day schedule. Post-construction settlement measured at 6 mm against a 25 mm allowance across the first winter of operation.